The building work for a typical house extension runs from a number of weeks to a few months, depending mainly on its size, whether it is one or two storeys and what goes inside it. Before any of that, allow time for drawings and approvals, which often take longer than people expect. A realistic timeline for your own project can only come from someone who has seen the house and the plans.
Two clocks: the paperwork and the build
When people ask how long an extension takes, they usually mean the time with builders on site. In practice there are two separate periods. The first is design and approvals, when nothing visible happens at the house. The second is construction, from the first spade in the ground to the day the new room is ready to decorate.
Planning the first period well makes the second run more smoothly. Rushing into a build before the drawings, structural details and approvals are settled is one of the most common causes of stop-start work later.
Before work starts on site
Most extensions begin with measured drawings of the existing house and proposed plans for the new space. From there, the route depends on what you are building. Some projects fall within permitted development; others need a full planning application to the local council, which then has a set period to decide. Our guide on extension planning permission explains how to tell which applies.
Building regulations approval is needed whichever route you take, and usually involves structural calculations for steels and foundations. If the work sits on or near a shared boundary, the party wall process may apply, and that has its own notice periods. Choosing between a rear, side or wraparound design is also part of this stage; see types of house extension for the options.
- Measured survey and drawings
- Permitted development check or planning application
- Building regulations and structural details
- Party wall notices where needed
- Choosing materials, windows and roof finish
Stage by stage on site
Once approvals are in place, an extension follows a fairly fixed order. Each stage has to be finished, and sometimes inspected, before the next can begin, which is why the sequence matters as much as the speed.
Groundwork comes first: marking out, digging the trenches and pouring the footings. Below-ground drainage is laid next, often linking into the existing system. The walls then rise in brick and block up to roof height, with lintels over the openings. After that the roof structure goes on and is made weatherproof, followed by the windows and external doors.
With the new shell sealed against the weather, the existing back or side wall is opened up and supported with steel. Electrics and plumbing are run in at first fix, the walls and ceilings are plastered, and second fix and finishing complete the room.
- Groundwork and footings
- Below-ground drainage
- Brick and block shell
- Roof and weatherproofing
- Windows and doors
- Knock-through and steels
- First fix, plastering and finishing
What makes one extension take longer than another
Size is the obvious factor, but it is not the only one. A single storey extension generally takes less time than a two storey one, since there is one level of walls, no upper floor structure and a simpler roof. A kitchen extension adds drainage for sinks and appliances, more services and the fitting of the kitchen itself.
Weather plays a part, particularly during groundwork and roofing. Ground conditions matter too: soft or clay soil, tree roots or a drain in the wrong place can mean deeper or redesigned foundations. Steel beams are made to order, so their lead time needs to be built into the programme. Finally, decisions you make along the way, such as changing a window size or waiting for a particular floor or kitchen, can add time.
Living at home while the work goes on
Many families stay in the house throughout. Because the first stages happen outside, the inside of the home is barely affected for much of the build. The disruptive part is the knock-through, when the old wall comes out and the two spaces are joined; there is noise and dust, and the kitchen may be out of action for a while if that is the room being extended.
Agreeing working hours, where materials will be stored and how the site is kept tidy before work begins makes living alongside an extension much easier.
Getting a realistic timeline for your project
General guidance only goes so far. The length of your build depends on your house, your ground, your access and your design. George Halliwell will look at all of those at a site visit, then explain the order of work and the likely timing as part of the quote. Read more about our house extensions, or get in touch to arrange a visit.
Want a professional to handle it?
Let's make it happen.
Tell George what you're planning and let's talk through the possibilities for your home.
Frequently asked questions
Does a single storey extension take less time than two storey?
Generally, yes. There is only one level of walls and a simpler roof, whereas a two storey extension adds an upper floor, more brickwork and often a more complex roof.
Can you build an extension in winter?
Yes, much of the work can carry on through winter, although very wet or freezing weather can pause concrete pours, brickwork and roofing for a few days at a time.
When is the wall knocked through?
Usually once the new extension is built and weathertight, so the house is open to the new space for as short a time as possible.
How long does planning permission take?
Councils have set target periods for deciding applications, but the full process, including drawings and any changes, often takes longer. Check current timings with your local council.
Can I stay in the house during the build?
Most people do. The early stages happen outside, and the main disruption comes during the knock-through and internal finishing.